From 25th to 28th February was placed concrete for the foundation slab of engine room No. 5. The slabs dimensions are 51 x 108 m and a variable height from 1.7m to 3.5m.
From 2nd to 5th February was placed concrete for the foundation slab of engine room No. 6. The slabs dimensions are 51 x 108 m and a variable height from 1.7m to 3.5m.
The beginning of work on the construction of Thermal Waste Treatment Plant in Kraków was on December 2013. To this day are made reinforced concrete works of three main buildings included in the project.
On December 23rd 2014 MOSTOSTAL ZABRZE Gliwickie Przedsiębiorstwo Budownictwa Przemysłowego Spółka Akcyjna signed an agreement for: “Construction of IT Center in Silesian University of Technology and Health Clinic with land development” in Gliwice.