Placing concrete for the foundation slab of engine room No. 6 in Power Plant Opole
From 2nd to 5th February was placed concrete for the foundation slab of engine room No. 6. The slabs dimensions are 51 x 108 m and a variable height from 1.7m to 3.5m. Placing the concrete was done using 5 pumps, 24 hours a day and lasted 80 hours. The total amount of used concrete was about 11 000 m3. Currently, the foundation slab of the engine room No. 5 is being reinforced.