Construction of Thermal Waste Treatment Plant in Kraków
The beginning of work on the construction of Thermal Waste Treatment Plant in Kraków was on December 2013. To this day are made reinforced concrete works of three main buildings included in the project. The currently scope of work is execution of masonry, plaster, industrial flooring and sewerage system.
Anticipated completion date of finishing work is May 31st 2015.
The total value of work performed by Mostostal Zabrze Gliwickie Przedsiębiorstwo Budownictwa Przemysłowego Spółka Akcyjna is approx. 50.5 mln PLN.